Document Review (renewals)
Replacements for expiring and expired documents, and new copies, waiting for a reviewer.
Document Review is under Review in the top bar, for HR and EHS reviewers, with the number waiting. A Customer Administrator is an HR and EHS reviewer by default, so has it too. A Report Viewer does not: deciding renewals is not a reader's job.
Tabs, each with its count: All renewals, HR review and EHS review. HR sees renewals of the HR items in its scope, EHS those of the EHS items. Your own record is never in your queue. The queue is in the order the replacements were submitted, oldest first; it has no search or filters. On a phone the queue is the page: tap a renewal to open it.
Where renewals come from
When a document on an approved record comes within its expiring-soon window (30 days unless the question sets another), a renewal opens and the Worker, or their Contractor Admin, can upload the replacement early. It lands here rather than reopening the whole record.
Until you approve it, the old approved document is still the document: it counts until it expires, and the replacement is not used anywhere, not even offered for reuse.
Deciding
Each row shows the Worker, HR or EHS, the requirement, the Contractor and Project, when the current document expires or expired (or why a new copy is needed) and when the replacement was submitted. The Worker's email is shown on HR renewals. On an EHS renewal it is left out, because EHS reviewers see basic Worker data only; only Obtempera's System Administrators see it there. Open one for the Replacement evidence: Preview replacement and Download, with the replacement's expiry date. While its virus check runs it reads Being checked — available in a few minutes and cannot be opened or approved.
- Approve replacement — it becomes the current document. The replacement must expire later than the document it replaces, must have the expiry date its question needs, must not have expired already, and must have passed the virus check. A Reviewer note is optional.
- Return to Worker — the note is required. The old document stays in place; the Worker is emailed your reason and asked again.
What it does to the Worker's status
While the old required document is only expiring soon, the Worker stays Compliant and cleared for site, shown Amber and flagged renewal due. If a required document expires without an approved replacement, the Worker is non-compliant (Red, not cleared for site) on that Project from midnight at the end of its expiry date, in the Project's country, within a minute: they see Not compliant – renewal needed, and reviewers' pages show Not compliant. Your approval of the renewal returns them at once to where they were (Compliant, or Training outstanding), without reviewing the rest of the record. An optional document never changes the Worker's status: it is renewed here all the same, and the reminders carry on.
New copies
An approved required document can also stop counting before it expires: the malware scan blocked its file, or it was recorded without the expiry date its question needs. The Worker is non-compliant on that Project, and a renewal opens here asking for a new copy; the Worker and their Contractor Admin are told at once, and reminded weekly, as for an expired document. The queue shows why instead of an expiry date (New copy: the security scan blocked the approved file, or New copy: the approved document had no expiry date). A new copy of a blocked file may carry the same expiry date as the old one (it must still be in date); one recorded without an expiry date must now have one. Approve it and the Worker returns, as for a renewal.